Current Construction Projects

 

Follow the progress of Bill and Hillary Clinton National Airport's construction projects.

 
More on other projects:

Project # 80007: Airfield Drainage Improvement
Project Budget: TBD
Contractor: TBD
Start Date: TBD
Completed: TBD
About this Project : This project is currently in the design Phase (LPA)

Project # 70011: SMGCS (Surface Movement Guidance Control System)
Project Budget: TBD
Contractor: Rick McGinty Company, Inc.
Start Date: 12/1/2008
Completed: Under Construction
About this Project : This project is to enhance night visibility and visibility during inclement weather. Currently, there are only edge lights on the east side of Taxiway A. This project will install edge and centerline lighting on Taxiway A, centerline lighting on Taxiway B from the General Aviation apron to C/B intersection, and centerline lighting from P/C intersection to Runway 22R. These lights will also be used during SMGS conditions. The lighting control panel in the ATC Tower will be modified.

Project # 70002: RW 18/36 Extension Phase IV
Project Budget: TBD 
Contractor: Redstone Construction
Start Date: 9/4/2007
Completed: Under Construction
About this Project : This project is proposed to extend Runway 18-36, 1,100 feet to the north. This will provide 6,224 feet of runway surface for aircraft arrivals and departures. The extension is needed to facilitate the separation of general aviation and commercial service aircraft. The environmental assessment for 18-36 was completed in July 2003 with an issuance of the Finding of No Significant Impact.

Project # 80001: RW 18/36 Extension Phase V
Project Budget: TBD
Contractor: Weaver Bailey
Start Date: 10/13/08
Completed: Under Construction
About this Project :This stage of the project involves construction of the 1,100 foot runway extension, stubouts for the future supporting taxiway system, completion of runway safety area grading, and the completion of perimeter road construction. Ancillary items include grading, storm drainage, concrete and asphalt paving, and temporary lighting and marking for construction safety.

Project # 80009: RW18/36 Extension Phase VI
Project Budget: TBD
Contractor: APAC of TN, 
Start Date: TBD
Completed: Under Construction
About this Project :  This stage of the project involves the construction of the remaining portions of Taxiway A, Taxiway P, Taxiway Z East, and Taxiway Z West with associated grading and drainage; reconstruction of the apron area west of Taxiway A along with the demolition of the existing State Police Hanger; construction of a new perimeter fence along the edge of proposed apron pavement. Ancillary items include grading, storm drainage, concrete and asphalt paving, lighting and marking.

Project # 90007: Taxiway Romeo Repair
Project Budget: TBD
Contractor: RK General Contracting
Start date: TBD
Completed: TBD
About this project: Remove deep deposits of unsuitable (soft, yielding) material that has been found under a section of Taxiway R. Preliminary geotechnical investigations indicate that the unsuitable material extends longitudinally for an estimated 400 LF. The 22” Portland Concrete Cement pavement will be removed in this area; the unsuitable material will be excavated and disposed; suitable material will be back-filled and the pavement replaced. Ancillary work includes replacement of the pipe under-drain system along both pavement edges, some of the taxiway edge lighting system, and restoration of the easterly portion of the taxiway safety area.

*All budgets are total costs (Admin., Engineering, and construction are included).